Counties/Dubrovnik-Neretva
Dubrovnik-Neretva CountyWho to ask before you buy land for solar
Six questions, in the order you need them.
- 01
Does the plan allow a solar plant here?
The county planning institute keeps the county plan and knows each municipal plan. Ask which zone your parcels are in and whether it takes a solar plant. The official answer is a lokacijska informacija from the office that issues permits there (the county office, or the city office in a large town): up to five parcels per request, within 15 days.
Dubrovnik-Neretva County spatial planning instituteZavod za prostorno uređenje Dubrovačko-neretvanske županijePetilovrijenci 2, 20000 Dubrovnikzzpudnz.hr ↗zzpudnz@zzpudnz.hr+385 (0)20 322 800ISPU geoportal: every spatial plan on one mapispu.mgipu.hr ↗ - 02
Can the grid take it?
Under 10 MW you connect to HEP ODS through the area office below. From 10 MW it is HOPS, the transmission operator, unless both agree otherwise; from 20 MW always HOPS.
HEP ODS distribution area SplitHEP ODS d.o.o. Elektrodalmacija SplitPoljička cesta 73, 21000 Splithep.hr ↗info.dpsplit@hep.hr0800 300 413HEP ODS distribution area DubrovnikHEP ODS d.o.o. Elektrojug DubrovnikNikole Tesle 3, 20000 Dubrovnikhep.hr ↗info.dpdubrovnik@hep.hr0800 300 416Croatian Transmission System Operator (HOPS)hops.hr ↗ - 03
Who owns the land?
The cadastre shows the parcel and its area; the land register at the municipal court shows the owner and any mortgage or lease.
State Geodetic Administration - Regional Cadastre Office DubrovnikDržavna geodetska uprava, Područni ured za katastar DubrovnikAnte Starčevića 23, 20000 Dubrovnikdgu.gov.hr ↗(020) 358 258Dubrovnik Municipal Court - land registry departmentsOpćinski sud u Dubrovniku - zemljišnoknjižni odjeliDr. Ante Starčevića 23, 20000 Dubrovniksudovi.hr ↗zemljisnoknjizni-odjel@osdu.pravosudje.hr020/448-116Metković Municipal Court - land registry departmentsOpćinski sud u Metkoviću - zemljišnoknjižni odjeliAndrije Hebranga 9, 20350 Metkovićsudovi.hr ↗+385 20 642-605Land register offices 5
- DubrovnikDr. Ante Starčevića 23, 20000 Dubrovnik020/448-116zemljisnoknjizni-odjel@osdu.pravosudje.hr
- KorčulaŠetalište Frana Kršinića 50, 20260 Korčula+385 20 711-445
- BlatoPP 52, 20271 Blato (postal address)
- MetkovićAndrije Hebranga 9, 20350 Metković+385 20 642-605
- PločeVladimira Nazora 14, Ploče+385 20 670-888
Uređena zemlja: cadastre and land register onlineoss.uredjenazemlja.hr ↗ - 04
Does it need an environmental screening?
It goes by the area of the plant. Under 10 ha the county office gives an opinion on request; the Ministry screens it only in forest, in protected nature or with similar plants within 5 km. From 10 to 100 ha the Ministry screens it; from 100 ha a full assessment.
Ministry of Environmental Protection and Green Transitionmzozt.gov.hr ↗ - 05
Who issues the permits?
A location permit is needed at any size. Under 10 MW it comes from the city office in the large towns, otherwise from the county office below, and no building permit is needed when property relations are settled. From 10 to 20 MW the county office issues the permits, from 20 MW the Ministry.
Dubrovnik-Neretva County building permits departmentDubrovačko-neretvanska županija – Upravni odjel za prostorno uređenje i gradnjuVukovarska 16, Dubrovnikdnz.hr ↗020/ 414-457Branch and city offices 6
- Gruda020/441-744
- KorčulaUlica Foša br. 1, Korčula020/ 711-722
- MetkovićUlica kralja Zvonimira 4, Metković020/ 676-450
- PločeTrg kralja Tomislava 7, Ploče020/ 676-444
- Vela LukaObala 3 br. 19, Vela Luka020/ 814-017
- City of DubrovnikZeljarica 1, Dubrovnik020/ 351-800dozvole@dubrovnik.hr
- 06
Who helps investors here?
The county development agency knows local land, programmes and people. The county administration is the general contact.
Dubrovnik-Neretva County regional development agency (regional coordinator)Regionalna razvojna agencija Dubrovačko-neretvanske županije - DUNEABranitelja Dubrovnika 41, 20000 Dubrovnikdunea.hr ↗info@dunea.hr+385 20 312 714Dubrovnik-Neretva County administrationDubrovačko-neretvanska županijaGundulićeva poljana 1, 20000 Dubrovnikdnz.hr ↗pisarnica@dnz.hr020/351-400
What moves here. As of November 2026.
solar plants filed for environmental screening at the Ministry since 2025, 3 of them in the last year.
- Jun 2026decided
- May 2026decided
- Mar 2026pending
municipal or county spatial plans went through a public hearing in the last year. A hearing is when a solar zone can appear or vanish.
- planhearing
- planhearing
- planhearing
substations have room for new plants in the HEP ODS table of November 2026.
- Komolacmore than 20 MW
- Opuzenmore than 20 MW
- Srđmore than 20 MW
- Blatoup to 20 MW
Names, municipalities and deadlines come to you as alerts.
Monitor · €199/month ↗Licensed professionals, from the official registers.
Looking for land in Dubrovnik-Neretva?
We find sites in zones the law lists for solar near a substation that still has room, and show how a plant there connects, how much can connect and what is still open: the plan, the grid and the land register.
Contacts come from official lists and the institutions' own sites, checked November 2026. If one is out of date, tell us.