Guides/Where a solar farm can be permitted in Croatia from 2026

Where a solar farm can be permitted in Croatia from 2026

Updated 24 November 2026 · Not legal advice.

Since 1 January 2026 Croatia has a new Spatial Planning Act (Zakon o prostornom uređenju, NN 155/25). For ground-mounted solar the main change is easy to state: a permit can be issued only on areas the Act itself lists. Free grid capacity and a willing landowner do not help if the parcel is not on that list.

The rule

Article 148(7) says that the permit for a solar plant or an agrisolar plant is issued in line with paragraph 1 of the same article and only on the areas defined in Article 19(1), items 41 and 42. Paragraph 1 requires every permit to follow the Act, the spatial plan and special regulations.

So a parcel has to pass two tests. It must fall in one of the listed areas. And the plan and other rules (nature, water, heritage) must not stop a plant there.

Where a plan contradicts the Act, the Act applies (Article 148(2)). In our reading, an older municipal plan that allowed solar “outside the building area on P3 land” without drawing a zone no longer opens a parcel on its own. The exception is the transition rule for older projects, described below.

The seven areas in item 41

  1. Zones drawn for solar on a plan map (41a). A plan of any level counts, and the zone can lie inside or outside the building area. On such zones the power limits written in the plan do not apply. The Act carves out especially valuable (P1) and valuable (P2) arable land; the Government’s explanatory note reads this as meaning such zones cannot lie on P1 or P2.
  2. Zones for economic use outside settlements, marked I or K (41b).
  3. P3 farmland directly next to such a zone (41c), if the zone has existing economic or business buildings. The plant may take at most 50% of the zone’s area, and the power is used by those buildings.
  4. Quarry lakes, fishponds and other inland aquaculture outside Natura 2000 (41d), with the consent of the concession grantor or lessor where there is one.
  5. Closed landfills (41e).
  6. Exploitation fields of solid minerals (41f), with prior consent of the mining authority.
  7. Plots of existing infrastructure and water structures (41g), with consent of the body that manages them.

Item 41c is written for a plant that supplies the buildings in the zone. In our reading it does not cover a plant built to sell power into the grid.

What a “zone for economic use outside settlements” is

The Croatian term is izdvojeno građevinsko područje izvan naselja gospodarske i poslovne namjene. Article 19(1), item 18, defines a separate building area outside a settlement as a unit the plan sets apart from the settlement’s building area and plans for any use except housing. On plan maps these zones carry the letter I (production) or K (business).

Three things follow:

Agrisolar on farmland, except P1 and P2

Item 42 allows an agrisolar plant (agrosunčana elektrana) on land a plan marks as agricultural, under four conditions:

P1, P2 and P3 come from a soil scoring system: P1 scores 80 to 100 points, P2 60 to 79, P3 40 to 59 (Pravilnik NN 23/19). The Agricultural Land Act also keeps P1 and P2 outside building areas for farming, and its exception for cases where no poorer land is nearby expressly does not cover stand-alone solar plants (Article 22(3)). There is no national digital map of P1 and P2. The category that counts is the one drawn on the plan sheet.

Item 42 does not exclude Natura 2000, but in our reading a plant there will need an appropriate assessment under nature protection law. For agrisolar the energy approval is issued without a public tender (Uredba NN 70/23, Article 18(1)).

The 1,000 m coastal strip

The Act defines a restricted area (prostor ograničenja): land and islands within 1,000 m of the coastline, plus a 300 m strip of sea (Article 19(1), item 48). Article 61 forbids plans and permits there for producing electricity from wind or sun, except PV panels integrated on buildings and car parks. Solar plants are also barred on maritime domain (pomorsko dobro, Article 69(5)) and at sea (Article 71(5)).

On the coast, a parcel within 1,000 m of the coastline is therefore closed to a ground-mounted plant, whatever the local plan shows.

Projects started before 2026

Article 242(3) keeps the old areas for one group: renewable projects that, before 1 January 2026, had applied for or received an environmental or nature protection decision, or held an energy approval. They may still be built on areas allowed by the previous Act if the location permit is applied for within five years, that is by 1 January 2031. Every other project works with the new list.

How to check a parcel

  1. List the plans in force. Usually the county plan (PPŽ) and the municipal or town plan (PPUO or PPUG), sometimes an urban development plan (UPU). Note any amendments in progress.
  2. Read the land-use sheet. On “Korištenje i namjena površina” look for a drawn solar zone, an I or K zone, or the farmland category. The building-area sheets, usually at 1:5,000, show the exact zone boundary.
  3. Read the protection sheets and the text. The “Uvjeti korištenja i zaštite prostora” sheets show nature, heritage, water and flood limits. The implementation provisions (odredbe za provedbu) often add setbacks or conditions for solar.
  4. Ask for a lokacijska informacija. Under Article 37, where no new-generation plan has been adopted, the administrative office (upravno tijelo) for the area issues it within 15 days, for up to five cadastral parcels per request. Article 19(1), item 58, defines that office: the department of the county, a large town or the City of Zagreb, or a local unit to which the county has passed this work. The document quotes the provisions of all plans in force for those parcels, and it states that it cannot be used to start works or prepare designs. Where a new-generation plan exists, the information can be produced electronically through the spatial planning information system.
  5. Check the cadastre and the land register for land use, area and encumbrances before you talk to owners.

A lokacijska informacija is the official statement of what the plans say for a parcel. It is not a permit, but no reading of a plan, ours included, replaces it.

How Gridplot helps

A Gridplot land search (€2,599 per search area) screens every parcel within 10 km of a substation with free capacity, keeps the land that lies in areas the Act lists, and groups it into sites of 5 ha or more. Each site comes with its plan zone and the plan’s own wording, and the three best sites come with their land register entries. If you have been offered land or a project, a land check (€490 per project) tells you within five working days what the plan says there, what the land register shows and whether the substation still has room. Both are reports compiled from public sources, not legal advice. See the products.

Sources

Privacy policy

Version 3, 24 November 2026

Who is responsible

Red Cat Labs d.o.o., Ulica Petra Hektorovića 2, Zagreb, Croatia, OIB 00036628211, runs Gridplot and is the controller of the personal data described here. You can reach us by post at that address or through the form on this site. Our full company details are in the Legal notice.

Requests sent through the form

The form asks for your company, the project type and size, the place where you want to build and your e-mail address or phone number. Only the e-mail address or phone number is required. With your request we record the date and time, the version of this policy and whether you asked for news. Cloudflare also tells us the country your connection comes from, based on your IP address. We do not receive the IP address itself.

We use these details to answer you, to send a free first look and to prepare an offer. The legal basis is the steps you ask for before a contract (Art. 6(1)(b) GDPR) and, where you write for a company, our legitimate interest in answering business enquiries (Art. 6(1)(f) GDPR). We use the country to spot misuse of the form and to see where requests come from, which is also our legitimate interest.

We send you news about Gridplot, at most once a month, only if you tick that separate box. The legal basis is your consent (Art. 6(1)(a) GDPR and the Croatian Electronic Communications Act). You can withdraw it at any time by replying to any message or by writing to us.

How your request reaches us

The site runs on Cloudflare (Cloudflare, Inc.). When you send the form, a Cloudflare Pages Function checks it and passes it straight on as a message to our team's chat in Telegram. We do not store the request on the site or at Cloudflare. Only members of our team in that chat can see it.

Telegram is a messaging service of Telegram Messenger Inc., a company established outside the European Economic Area (EEA). Telegram keeps the message on its servers until we delete it. Its privacy policy says that data of users who signed up in the EEA is held in data centres in the Netherlands, but the company that controls those servers is outside the EEA. We therefore treat sending your request to Telegram as a transfer outside the EEA.

This transfer is not covered by an adequacy decision of the European Commission, and we have no data processing agreement or standard contractual clauses with Telegram. Your data may therefore be less well protected than in the EU, and you may find it harder to enforce your rights against Telegram.

We rely on your explicit consent to this transfer (Art. 49(1)(a) GDPR), which you give by ticking the required box in the form. If you do not want your request to go through Telegram, do not use the form. Write to us by post instead.

We delete your request from the chat within 24 months after our last contact with you, or sooner if you ask.

Clients and orders

When your company orders from us, we process the names, roles and business contact details of the people we deal with, the order, our correspondence, invoices and payments. The legal bases are the contract (Art. 6(1)(b) GDPR), our legal duties in accounting and tax (Art. 6(1)(c) GDPR) and our legitimate interest in keeping a record of what we delivered (Art. 6(1)(f) GDPR).

Invoices may pass through an authorised e-invoice intermediary and are reported to the Croatian Tax Administration (Porezna uprava) as the law requires. Monitor alerts go to the contacts you give us.

We keep invoices and accounting records for as long as Croatian accounting and tax law requires. We keep reports, offers and correspondence for 5 years after delivery, so that we can deal with corrections and claims.

Landowners in our reports

When a client orders a report, we read the land register (zemljišne knjige) and the cadastre by hand for the parcels of that order. These public registers show owners' names, addresses and OIB, ownership shares and entries such as mortgages. We read them only for a client's order and we do not run bulk queries.

We use this data only for that order. The report describes the land register entries without naming anyone. Only if the client asks, a separate annex gives the names, addresses and OIB of the owners of the parcels concerned. The legal basis is the legitimate interest of the client and of Red Cat Labs d.o.o. in assessing land for energy projects (Art. 6(1)(f) GDPR). The data comes from public registers, covers only the parcels ordered and is not used for anything else.

We never contact owners, on our own account or on a client's behalf. We do not build databases of owners and we do not collect phone numbers or other contact details. A client that receives the annex becomes a separate controller and may use the data only to assess the land and to buy or lease it (see our Terms of service).

We keep owners' names, addresses and OIB and the land register extracts for 12 months after we deliver the report, and then delete them. We keep the report itself, which names no owners, for 5 years.

We do not inform each owner individually. We hold no contact details for owners and would have to collect more data to reach them (Art. 14(5)(b) GDPR). We publish this policy to inform them instead.

If you own land and object to this use, write to us. We will stop using your data unless we need it to establish, exercise or defend a legal claim.

Visiting the site

When you visit the site, Cloudflare processes your IP address and technical data about your browser to deliver the pages and protect them from attacks. The legal basis is our legitimate interest in running a secure site (Art. 6(1)(f) GDPR). Cloudflare acts as our processor. Where data goes to the United States, it relies on the EU-US Data Privacy Framework.

Cookies and tracking

Necessary, always on: your cookie choice, kept in your browser's local storage under gridplot-consent. The form's protection against bots stores nothing on your device. None of this tracks you.

Statistics and marketing tools run only after you agree to their category. Until then they do not load. The legal basis is your consent (Art. 6(1)(a) GDPR and the Croatian Electronic Communications Act). You can change or withdraw it at any time under "Cookie settings" at the bottom of the page. We then delete these tools' cookies from your browser.

Google may process this data in the United States under the EU-US Data Privacy Framework.

Fonts are served from this site, so no font request goes to a third party.

Who receives your data

We do not sell personal data.

Your rights

You can ask for access to your data, correction, deletion, restriction of processing and a copy to take elsewhere. You can object to processing based on legitimate interest. Where we rely on your consent, you can withdraw it at any time. This does not affect processing that happened before.

Send a letter to our address or use the form on this site. We answer within one month, free of charge. We may ask you to confirm who you are.

We take no decisions about you based solely on automated processing.

You can complain to the Croatian supervisory authority, Agencija za zaštitu osobnih podataka (AZOP), Selska cesta 136, Zagreb, azop.hr.

Changes

We publish changes to this policy on this page, with a new version number and date.

Legal notice

Version 3, 24 November 2026

Service provider

Gridplot is a service of Red Cat Labs d.o.o., a limited liability company (društvo s ograničenom odgovornošću) under Croatian law.

What our reports and alerts are

Reports and alerts supplied under the name Gridplot compile information from public and official sources, processed partly by automated means. Each one states the date on which each source was read and describes that source on that date only.

They are not legal, tax, technical, valuation, surveying or investment advice. They are not a title opinion, an act or opinion of a public authority, or an offer, reservation or commitment of a grid operator. Capacity figures are estimates published by HEP ODS and HOPS and reserve no capacity.

We do not warrant that the sources are complete, current or correct, and we do not check them on site. Where a plan or a regulation can be read in more than one way, the report marks the reading as our own.

Before entering into any binding obligation, obtain a location information (lokacijska informacija) from the competent authority, a lawyer's review of the land register, a survey by a licensed surveyor and the connection terms of the grid operator.

Gridplot never contacts landowners or authorities on a client's behalf. Red Cat Labs d.o.o. is not affiliated with HEP ODS, HOPS or any public authority.

This website

This site describes our services in general terms and is not an offer in the legal sense. What we deliver, and on what terms, is set by a written offer and our Terms of service. Prices are stated exclusive of VAT.

How we handle personal data and cookies is explained in our Privacy policy.

We are not responsible for the content of external sites we link to.

Texts, design and software of this site: © Red Cat Labs d.o.o.

Map data

© OpenStreetMap contributors (ODbL). © ESA WorldCover project 2021, contains modified Copernicus Sentinel data (2021) processed by ESA WorldCover consortium (CC BY 4.0). Global Wind Atlas 4.0, DTU (CC BY 4.0). Elevation model of the State Geodetic Administration, DGU (Otvorena dozvola).

Terms of service

Version 3, 24 November 2026

1. Who we are and who these Terms are for

Gridplot is a service of Red Cat Labs d.o.o., Ulica Petra Hektorovića 2, Zagreb, Croatia, OIB 00036628211 ("we"). Our full company details are in the Legal notice.

We sell only to businesses: companies and other persons who order in the course of their trade or profession. We do not make contracts with consumers. With each order we ask for your company's OIB or VAT number.

These Terms apply to our free first look, to every offer and to every order for Land search, Land check and Monitor.

2. What we do

We help you find and check land near substations with free grid capacity for ground-mounted solar plants in Croatia. Our software screens public and official sources for the area you name. For the sites in your order we read the land register by hand.

A report compiles what public records show. For each figure it gives the source, a public link where one exists, the date we read the source and how we got the figure: copied from the source, calculated by us or read by hand. Where a plan or a regulation can be read in more than one way, the report marks the text as our reading. The report also lists what we did not check.

Reports do not reproduce sheets of spatial plans or images from the ISPU portal. They cite the plan and say what it states. The plan itself is available in its official publication and from the competent authority.

3. What we do not do

We never contact landowners, public authorities or grid operators on your behalf. We do not negotiate for you, we do not act as an agent in land deals and we take no fee linked to a deal. Our price covers our work. It does not depend on the number of sites we find or on any deal you make.

We do not visit the land and we cannot correct errors in public registers.

4. What a report is not

A report is a compilation of public records with sources and dates. It is not legal advice, a title opinion, a valuation, a survey, a design, a permit or other act of a public authority, a grid connection offer or investment advice.

We do not guarantee that a permit will be issued, that grid capacity will still be free when you apply, or that any land can be bought or leased. Capacity figures are estimates published by HEP ODS and HOPS. They reserve nothing. Only the grid operator's connection study and the connection contract fix the terms of a connection.

Before you commit money, confirm the zoning with a location information (lokacijska informacija) from the competent authority, the title with a lawyer's review of the land register, the boundaries with a licensed surveyor and the connection terms with the grid operator.

5. Services and prices

All prices exclude VAT.

The offer states the service, the search area or project, the number of sites with a land register reading, the price and the delivery time. If the offer and these Terms differ, the offer prevails.

6. How a contract is made

You send a request through the form on our site or by e-mail. By ticking the required box in the form you accept these Terms for your request and for our free first look.

We may reply with a free first look, a short note on the area. It is not advice and creates no obligation for either side. We are not liable for it, except for intent or gross negligence.

If you want a report, we send a written offer that refers to these Terms. The contract is made when you accept the offer in writing, by signing it or by confirming it by e-mail. These Terms, in the version named in the offer, then form part of the contract. Your own general terms do not apply unless we accept them in writing.

7. Payment and invoices

We send an invoice when you accept the offer. You pay it before delivery, to the IBAN shown on the invoice and in the Legal notice. Monitor is invoiced monthly in advance.

Prices exclude VAT. We charge VAT as the law requires, including under the reverse charge where it applies. If a tax authority later finds that Croatian VAT was due on a service, you pay that VAT on top of the price.

We issue invoices in the form the law requires, including e-invoices (eRačun) where the Croatian fiscalisation rules apply. Please give us your OIB or VAT number, your billing address and, if you have one, your address for receiving e-invoices.

If you pay late, we may charge statutory default interest and hold delivery until the payment arrives.

8. Delivery

We deliver a Land search or a Land check within 5 working days after your payment reaches us, unless the offer states another time. We deliver electronically.

If a source we need is unavailable, or you have not given us what we need, we tell you and agree a new date with you.

Monitor alerts go to the contact you name. We check the sources regularly, but sources can publish late, change their format or go offline, so an alert can come late. Each alert says what the source showed on the date stated.

9. Monitor pilot

Monitor runs month by month. You can end it at any time, with effect from the end of the month you have paid for.

Because Monitor is a pilot, its features may change. We tell you in writing at least 30 days before we change the price or end the pilot, and you can end Monitor before the change takes effect.

10. Corrections

If a figure in a report or an alert does not match its cited source on the cited date, tell us and we correct it free of charge. Tell us within 12 months of delivery, by post or through the form on this site, and name the figure and the source.

A difference between a source and the situation on the ground, or a change in a source after the cited date, is not an error in the report.

11. Liability

We prepare every report with care. For ordinary negligence our liability is limited to the price you paid for the service concerned. For Monitor it is limited to the fees you paid in the 12 months before the event that caused the loss. We are not liable for indirect loss or lost profit.

These limits do not apply to loss caused by intent or gross negligence, or to any other liability that Croatian law does not allow to be limited (Article 345 of the Civil Obligations Act, Zakon o obveznim odnosima).

Only the company that ordered a report may rely on it. Anyone else, a lender or an investor for example, may rely on it only with our written consent.

12. Your licence to use the report

We keep all rights in our reports, alerts, software and methods. Once you have paid, you receive a non-exclusive, non-transferable licence to use the report within your company, for the project or area in the order.

You may share the report with your own professional advisers who work on that project and are bound by confidentiality. You may not publish or resell the report or use it to build a database.

Map and source data in a report remain under their own licences, which the report lists. Keep their attributions when you use them.

13. Landowner data

Reports describe land register entries without naming owners. Names, addresses and OIB of owners are given only on request, in a separate annex, and only for the parcels of your order.

When you receive this annex you become a separate controller of that data under the GDPR. You may use it only to assess the land and to buy or lease it. You must give the owners the information required by Article 14 GDPR at the latest when you first contact them. You may not pass the data on or compile lists of owners, and you must delete it when you no longer need it for that purpose.

How we handle this data is explained in our Privacy policy.

14. Confidentiality

We keep confidential the fact that you are our client, the area you ask about and the details of your project, unless you agree to disclosure or the law requires it.

Reports compile public records and are not exclusive. We may report on the same area, substations or land for other clients.

15. Changes and notices

We may update these Terms. Each order is governed by the version named in its offer. For Monitor, a new version applies from the month after we tell you about it, and you may end Monitor before then.

We send notices to the e-mail address in the offer. Send yours by post to our address or to the e-mail address we use in the offer.

16. Language, law and courts

These Terms are published in Croatian and English. If the two versions differ, the Croatian version prevails.

Croatian law applies. Disputes go to the court with subject-matter jurisdiction in Zagreb.

Cookie settings

Choose what may run on this site. You can change this at any time with “Cookie settings” at the bottom of the page.

NecessaryAlways on

Remembers your choices on this page and protects the form from bots. No tracking.

Counts visits and shows us which pages people use. Records your IP address, device and browser.

Measures our ads and shows you Gridplot ads on other sites. Shares your IP address and an identifier with advertising networks.