Where a solar farm can be permitted in Croatia from 2026
Since 1 January 2026 Croatia has a new Spatial Planning Act (Zakon o prostornom uređenju, NN 155/25). For ground-mounted solar the main change is easy to state: a permit can be issued only on areas the Act itself lists. Free grid capacity and a willing landowner do not help if the parcel is not on that list.
The rule
Article 148(7) says that the permit for a solar plant or an agrisolar plant is issued in line with paragraph 1 of the same article and only on the areas defined in Article 19(1), items 41 and 42. Paragraph 1 requires every permit to follow the Act, the spatial plan and special regulations.
So a parcel has to pass two tests. It must fall in one of the listed areas. And the plan and other rules (nature, water, heritage) must not stop a plant there.
Where a plan contradicts the Act, the Act applies (Article 148(2)). In our reading, an older municipal plan that allowed solar “outside the building area on P3 land” without drawing a zone no longer opens a parcel on its own. The exception is the transition rule for older projects, described below.
The seven areas in item 41
- Zones drawn for solar on a plan map (41a). A plan of any level counts, and the zone can lie inside or outside the building area. On such zones the power limits written in the plan do not apply. The Act carves out especially valuable (P1) and valuable (P2) arable land; the Government’s explanatory note reads this as meaning such zones cannot lie on P1 or P2.
- Zones for economic use outside settlements, marked I or K (41b).
- P3 farmland directly next to such a zone (41c), if the zone has existing economic or business buildings. The plant may take at most 50% of the zone’s area, and the power is used by those buildings.
- Quarry lakes, fishponds and other inland aquaculture outside Natura 2000 (41d), with the consent of the concession grantor or lessor where there is one.
- Closed landfills (41e).
- Exploitation fields of solid minerals (41f), with prior consent of the mining authority.
- Plots of existing infrastructure and water structures (41g), with consent of the body that manages them.
Item 41c is written for a plant that supplies the buildings in the zone. In our reading it does not cover a plant built to sell power into the grid.
What a “zone for economic use outside settlements” is
The Croatian term is izdvojeno građevinsko područje izvan naselja gospodarske i poslovne namjene. Article 19(1), item 18, defines a separate building area outside a settlement as a unit the plan sets apart from the settlement’s building area and plans for any use except housing. On plan maps these zones carry the letter I (production) or K (business).
Three things follow:
- It is building land, not farmland.
- The zone must already exist in an adopted plan. New land joins the list only when the plan is amended.
- The Act sets no size limit for these zones, but the plan’s own conditions for the zone still apply, such as setbacks or the share of the zone a plant may take.
Agrisolar on farmland, except P1 and P2
Item 42 allows an agrisolar plant (agrosunčana elektrana) on land a plan marks as agricultural, under four conditions:
- the land is not P1 or P2;
- it is not in an area protected under nature protection law;
- it carries permanent crops entered in ARKOD, the farm land-use register;
- it keeps its agricultural use, and the plant serves the aims of farming.
P1, P2 and P3 come from a soil scoring system: P1 scores 80 to 100 points, P2 60 to 79, P3 40 to 59 (Pravilnik NN 23/19). The Agricultural Land Act also keeps P1 and P2 outside building areas for farming, and its exception for cases where no poorer land is nearby expressly does not cover stand-alone solar plants (Article 22(3)). There is no national digital map of P1 and P2. The category that counts is the one drawn on the plan sheet.
Item 42 does not exclude Natura 2000, but in our reading a plant there will need an appropriate assessment under nature protection law. For agrisolar the energy approval is issued without a public tender (Uredba NN 70/23, Article 18(1)).
The 1,000 m coastal strip
The Act defines a restricted area (prostor ograničenja): land and islands within 1,000 m of the coastline, plus a 300 m strip of sea (Article 19(1), item 48). Article 61 forbids plans and permits there for producing electricity from wind or sun, except PV panels integrated on buildings and car parks. Solar plants are also barred on maritime domain (pomorsko dobro, Article 69(5)) and at sea (Article 71(5)).
On the coast, a parcel within 1,000 m of the coastline is therefore closed to a ground-mounted plant, whatever the local plan shows.
Projects started before 2026
Article 242(3) keeps the old areas for one group: renewable projects that, before 1 January 2026, had applied for or received an environmental or nature protection decision, or held an energy approval. They may still be built on areas allowed by the previous Act if the location permit is applied for within five years, that is by 1 January 2031. Every other project works with the new list.
How to check a parcel
- List the plans in force. Usually the county plan (PPŽ) and the municipal or town plan (PPUO or PPUG), sometimes an urban development plan (UPU). Note any amendments in progress.
- Read the land-use sheet. On “Korištenje i namjena površina” look for a drawn solar zone, an I or K zone, or the farmland category. The building-area sheets, usually at 1:5,000, show the exact zone boundary.
- Read the protection sheets and the text. The “Uvjeti korištenja i zaštite prostora” sheets show nature, heritage, water and flood limits. The implementation provisions (odredbe za provedbu) often add setbacks or conditions for solar.
- Ask for a lokacijska informacija. Under Article 37, where no new-generation plan has been adopted, the administrative office (upravno tijelo) for the area issues it within 15 days, for up to five cadastral parcels per request. Article 19(1), item 58, defines that office: the department of the county, a large town or the City of Zagreb, or a local unit to which the county has passed this work. The document quotes the provisions of all plans in force for those parcels, and it states that it cannot be used to start works or prepare designs. Where a new-generation plan exists, the information can be produced electronically through the spatial planning information system.
- Check the cadastre and the land register for land use, area and encumbrances before you talk to owners.
A lokacijska informacija is the official statement of what the plans say for a parcel. It is not a permit, but no reading of a plan, ours included, replaces it.
How Gridplot helps
A Gridplot land search (€2,599 per search area) screens every parcel within 10 km of a substation with free capacity, keeps the land that lies in areas the Act lists, and groups it into sites of 5 ha or more. Each site comes with its plan zone and the plan’s own wording, and the three best sites come with their land register entries. If you have been offered land or a project, a land check (€490 per project) tells you within five working days what the plan says there, what the land register shows and whether the substation still has room. Both are reports compiled from public sources, not legal advice. See the products.
Sources
- Zakon o prostornom uređenju, NN 155/25: čl. 19 st. 1 t. 18, 41, 42, 48 and 58; čl. 37; čl. 61; čl. 69 st. 5; čl. 71 st. 5; čl. 148 st. 1, 2 and 7; čl. 242 st. 3
- Zakon o poljoprivrednom zemljištu, NN 20/18, 115/18, 98/19, 57/22, 136/25: čl. 22 st. 3
- Pravilnik o mjerilima za utvrđivanje osobito vrijednog obradivog (P1) i vrijednog obradivog (P2) poljoprivrednog zemljišta, NN 23/19: čl. 28
- Uredba o kriterijima za provođenje javnog natječaja za izdavanje energetskog odobrenja, NN 70/23: čl. 18 st. 1
- Zakon o zaštiti prirode, NN 80/13, 15/18, 14/19, 127/19: čl. 24