Solar plant permits in Croatia in 2026, step by step
From 2026 every ground-mounted solar plant in Croatia needs a location permit (lokacijska dozvola), whatever its size (Spatial Planning Act, NN 155/25, Article 154(1), item 12). What comes after it, and who decides, depends on the plant’s capacity. The environmental procedure depends on its area. Below is the sequence as we read the law in November 2026, with the open points.
1. Land in an area the law lists
A permit can be issued only on the areas in Article 19(1), items 41 and 42, and it must also follow the spatial plan (Article 148). Projects that had an environmental or nature decision, or a request for one, or an energy approval before 1 January 2026 may use the old areas if they apply for the location permit by 1 January 2031 (Article 242(3)).
2. Grid and energy approval
The location permit application must include three documents (Article 157(3)):
- the energy approval (energetsko odobrenje);
- a connection contract with the grid operator;
- the consent of the owner of the land, unless the applicant is a legal entity founded by the Republic of Croatia.
The grid steps (preliminary opinion, connection study, contract) take time, so they start early.
The energy approval under 10 MW is not settled. The Electricity Market Act (Article 16(1)) and the decree on energy approvals (Uredba NN 70/23, Article 19(4)) exempt plants that count as simple buildings (jednostavne građevine). Since 1 January 2026, however, the Spatial Planning Act asks for the energy approval with the location permit application of any power plant. We found no practice of the authorities that reconciles the two. Budget for the approval.
Where the approval is issued without a tender, the fee is 8.327 EUR per kW of connection capacity plus VAT, paid to HROTE within 15 days (Uredba NN 70/23, Article 18(11)). For 10 MW that is about €83,000 before VAT.
Above 10 MW the approval is always needed. It is issued without a tender where the investor has settled the property rights on the land, and for agrisolar plants. On land owned by the state or by local or regional government it goes through a public tender. For an approval without a tender, contracts and consents filed as proof must be solemnised by a notary (Article 18(8)). If no location permit follows within three years, the Ministry revokes the approval (Electricity Market Act, Article 17(27), consolidated text).
3. Environmental screening by area
The Decree on environmental impact assessment (NN 61/14, 3/17, with new annexes from NN 48/26, in force since 16 May 2026) sorts stand-alone solar plants by area:
| Plant area | Procedure | Who decides |
|---|---|---|
| 100 ha or more | full environmental impact assessment | Ministry |
| more than 10 ha and less than 100 ha | screening (OPUO) | Ministry |
| less than 10 ha, but on forest land, in an area protected under nature or water protection rules, or with similar existing or approved plants within 5 km | screening (OPUO) | Ministry |
| below these thresholds | on the developer’s request, an opinion on whether a significant negative effect is possible, or a screening | county office (City of Zagreb) |
The text says “more than 10 ha”, so a plant of exactly 10 ha with none of the three criteria falls in the last row. The screening decision is attached to the location permit application (ZPU Article 156(2)).
4. Natura 2000
Under the Nature Protection Act (Articles 24 to 33), a project that, alone or with others, may have a significant negative effect on the conservation objectives of a Natura 2000 site needs an appropriate assessment (ocjena prihvatljivosti za ekološku mrežu). It has stages: a screening (prethodna ocjena), a main assessment (glavna ocjena) where an effect cannot be excluded, and, as a last resort, a finding of overriding public interest with compensation.
- Where the plant goes through OPUO, the Natura screening is done inside it.
- Where neither OPUO nor a full assessment applies, the developer files a separate request for the screening.
- The assessment happens before the location permit, and the decision goes with the application.
- If the authority finds that a significant negative effect exists or cannot be excluded despite mitigation, it refuses the request.
Other bodies may set conditions too. Hrvatske vode issues water conditions (vodopravni uvjeti) in flood-risk areas and in sanitary protection zones of water sources, and the Ministry of Culture sets special conditions for work on or within protected heritage.
5. The location permit
| Capacity | Location permit issued by |
|---|---|
| under 10 MW | county office, or the large town on its own territory |
| 10 MW up to 20 MW | county office, also inside a large town |
| 20 MW or more | Ministry of Physical Planning, Construction and State Assets |
(Uredba NN 37/14, Articles 2 and 4; ZPU Articles 142 and 143.)
The application goes through the eDozvola system with the conceptual design (idejni projekt), the environmental and Natura decisions where required, and the three documents above.
The permit lapses if, within four years of becoming final, no building permit is applied for or, where none is needed, works do not start. If the Ministry issued it, the period is six years (Article 182).
6. Building permit, or none
Under 10 MW. Article 4, item 26, of the Rulebook on simple and other buildings and works (Pravilnik o jednostavnim i drugim građevinama i radovima) allows a grid-connected solar or agrisolar plant with installed capacity up to 10 MW to be built without a building permit, on land where the investor has settled the property rights. Work follows the main design (glavni projekt) with the confirmations of public authorities, a notice of start of works and professional supervision.
The new Building Act (NN 155/25, Article 157, item 6) keeps this Rulebook in force until a replacement is adopted. A draft was in public consultation until 3 September 2026, and press reports say it keeps the rule. As of 23 November 2026 it had not been published in Narodne novine.
What counts as settled property rights is not defined. Our reading: ownership or a building right (pravo građenja), and probably a lease or the owner’s notarised consent, by analogy with the Building Act and the energy approval decree. Item 26 is not on the Rulebook’s list of works exempt from a use permit, so in our reading a use permit (uporabna dozvola) is still required.
From 10 MW. A building permit is needed: from the county for 10 to 20 MW, from the Ministry from 20 MW. It is valid for six years, eight if the Ministry issued it (Building Act, Article 79). For a building plot the investor shows ownership or a building right; where the location permit defines a project area (obuhvat zahvata) instead, a lease or servitude can be enough (Article 65).
The 10 MW line
The Rulebook says “up to 10 MW” and Uredba 37/14 says “from 10 MW”, so a plant of exactly 10.0 MW falls under both. The Rulebook does not define installed capacity. The 2023 incentives decree counts PV capacity as the sum of the inverters’ rated power. Our reading: stay below 10 MW measured at the inverters.
Below that line: no building permit, connection to HEP ODS, permits from the county or large town. At 10 MW: a building permit, HOPS by default, and the county even inside a large town.
How Gridplot helps
A land search (€2,599 per search area) finds sites of 5 ha or more near substations with room, in areas the law lists, and for each site sets out the plan’s wording, the nature, flood and heritage checks, the connection path and the fee. A land check (€490 per project) does the same for one site or project you have been offered, in five working days. Both are reports compiled from public sources, not legal advice or a permit decision. See the products.
Sources
- Zakon o prostornom uređenju, NN 155/25: čl. 19, 142, 143, 148, 154, 156, 157, 182, 242
- Zakon o gradnji, NN 155/25: čl. 53, 54, 65, 79, 157
- Pravilnik o jednostavnim i drugim građevinama i radovima, NN 112/17, 34/18, 36/19, 98/19, 31/20, 74/22, 155/23: čl. 4 t. 26, čl. 6
- Uredba o određivanju građevina, drugih zahvata u prostoru i površina državnog i područnog (regionalnog) značaja, NN 37/14, 154/14, 30/21, 75/22, 61/23: čl. 2, čl. 4
- Zakon o tržištu električne energije, NN 111/21, 83/23, 17/25, 114/26: čl. 16, 17
- Uredba o kriterijima za provođenje javnog natječaja za izdavanje energetskog odobrenja, NN 70/23: čl. 18, 19
- Uredba o poticanju proizvodnje električne energije iz obnovljivih izvora energije i visokoučinkovitih kogeneracija, NN 70/23: čl. 2
- Uredba o procjeni utjecaja zahvata na okoliš, NN 61/14, 3/17, 48/26: Prilog I t. 5, Prilog II t. 2.4, Prilog III t. 6
- Zakon o zaštiti prirode, NN 80/13, 15/18, 14/19, 127/19: čl. 24 to 33
- Zakon o vodama, NN 66/19, 84/21, 47/23: čl. 158
- Zakon o zaštiti i očuvanju kulturnih dobara, NN 145/24, 151/25: čl. 43, 44