Connecting a solar plant to the grid in Croatia: HEP ODS, HOPS and fees
In Croatia the grid comes before the permit. Since 2026 an application for a location permit for a power plant must include a connection contract with the grid operator, next to the energy approval and the landowner’s consent (Spatial Planning Act, NN 155/25, Article 157(3)). Below: who you connect to, how to read the HEP ODS capacity table, the steps and the fee.
HEP ODS or HOPS: size decides
The distribution grid code (Mrežna pravila distribucijskog sustava, NN 74/18, 52/20) sets the split:
- Article 28(1): a user with a connection capacity of 10 MW or more connects to the transmission grid run by HOPS, unless HOPS and HEP ODS jointly find a distribution connection justified.
- Article 28(2): the largest single plant that may connect to the distribution grid is 20 MW.
- Article 47: at medium voltage (MV), up to 10 MW can connect to an MV line, MV/MV busbars or a switching station. Up to and including 20 MW can connect to the MV busbars of a 110/x kV substation, if the connection study for 10 MW or more includes a transmission analysis done with HOPS.
| Connection capacity | Operator |
|---|---|
| under 10 MW | HEP ODS, medium voltage |
| 10 MW up to 20 MW | HOPS by default; HEP ODS at the MV busbars of a 110/x kV substation if both operators agree |
| over 20 MW | HOPS |
The HEP ODS capacity table
About once a month HEP ODS publishes an estimate of how much new generation each of its 148 supply substations (110/x kV) can take. It comes as PDF annexes and as a map on HEP’s website. Each substation gets a category:
| Category | What HEP ODS writes |
|---|---|
| / | no room; until circumstances change, requests of 100 kW or more are not processed |
| A | up to 5 MW |
| B | up to 10 MW |
| C | up to 20 MW |
| D | more than 20 MW |
How to read it:
- The bands are ceilings. “A” means up to 5 MW and could mean far less. The table gives no MW figure for a substation.
- Nothing is reserved. HEP ODS calls the data an indicative guide that changes daily and does not replace the connection study, which sets the real terms.
- “D” does not open the door to a large plant. One plant on HEP ODS is capped at 20 MW, and from 10 MW the default is HOPS.
- The “upgraded substation” column is a scenario. It assumes the transformers are replaced with the largest standard size (40 MVA). No document says who pays for that or when.
- Only the 110/x kV level is assessed. MV lines and 35/10 kV substations are examined in the connection study.
- The method is not published. The public rule is Article 28(3): total generation on the MV grid fed from a substation may not exceed the transformer capacity left after the largest transformer fails, plus the minimum load at that node. Minimum loads are not published. In our reading this n-1 rule drives the categories, but HEP ODS has not said so in those words.
- A “/” substation that cannot be upgraded with standard solutions will take new plants, HEP ODS says, only after a new 110/x kV substation is built under the operators’ ten-year plans.
Since 15 October 2026 the amended Electricity Market Act (NN 114/26) requires distribution operators to publish capacity for new connections in fine spatial detail, with the calculation criteria, at least every six months. HERA must also adopt rules for flexible connections. By late November 2026 we had seen neither. The same amendments require connection contracts signed without a final connection deadline to be terminated within four years; in our reading this may free some queued capacity over time.
HOPS publishes its own table for the transmission grid, with bands of up to 50 MW, up to 100 MW and over 100 MW. The latest edition on its website shows the state on 29 February 2024, with most nodes marked “/”. In a presentation on 3 November 2026, HOPS reported about 212 MW of solar in operation on its grid and about 3,005 MW of solar waiting: 699 MW with a connection contract and 2,306 MW at the connection study stage.
The steps with HEP ODS
HEP ODS describes this sequence for producers:
- Preliminary procedure. A connection feasibility study (Elaborat mogućnosti priključenja, EMP) and HEP ODS’s preliminary opinion on the possibility of connection (preliminarno mišljenje o mogućnosti priključenja). Under HEP ODS’s 2023 connection rules the opinion is valid for one year and holds no capacity: if other plants sign contracts or start the procedure in the meantime, the room can be gone.
- Energy approval. With the preliminary opinion the investor applies to the Ministry of Economy. Whether plants under 10 MW need an approval is not settled; budget for it.
- Connection study (EOTRP). The investor requests the Elaborat optimalnog tehničkog rješenja priključenja. HEP ODS sends an offer within 15 days, and the investor accepts it by paying within 30 days. The study sets the technical solution, including any grid reinforcement.
- Decision and contract. HEP ODS decides whether the EOTRP is acceptable. The investor has one year from receiving the EOTRP to return a signed connection contract, or the study lapses.
- After the contract: the electricity consent (elektroenergetska suglasnost), confirmation of the main design, payment of the fee, building the connection and any grid works, a grid-use contract, energisation, trial operation and the certificate for permanent operation.
Requests go through HEP ODS’s online application “Moja mreža”, via an authorised study author. The 2023 rules may change soon: the 2026 amendments give operators six months from 15 October 2026 to align their acts.
If the EOTRP finds that the grid needs reinforcement, HEP ODS must consider an operational limit on the plant’s use of its connection capacity until the works are done. It is applied at the investor’s request through an addendum to the contract. Extra costs are charged at actual cost, and HEP ODS does not pay for energy lost to the limit until the agreed date for the works.
The connection fee
HERA set the unit prices that apply from 1 May 2026 (decision published in NN 45/2026). They exclude VAT and are the same across Croatia:
- Medium voltage: 96.50 EUR/kW paid to HEP ODS, plus 9.50 EUR/kW for the high-voltage grid, paid to HOPS.
- Low voltage: 193.00 EUR/kW.
- High voltage: the actual cost of the connection plus 19.00 EUR/kW.
At MV the two parts add up to 106 EUR/kW. For a 10 MW plant that is about €1.06 million before VAT, by our arithmetic; the exact capacity base comes from the formula in HERA’s methodology (NN 84/22). A non-standard connection adds its actual extra cost. HERA can reset the prices each year on the operators’ proposals, so the figure is not fixed. For 2026 HEP ODS had proposed 120 EUR/kW at MV and HOPS 72.51 EUR/kW for the high-voltage part; HERA rejected both.
How much can connect
The plant size is the smallest of four limits: the land, the plan’s conditions, the substation’s band, and 20 MW per plant on HEP ODS. The EOTRP then sets the final figure. The band alone tells you only where a study may be worth paying for.
How Gridplot helps
A land search (€2,599 per search area) starts from substations that still have room. For each site it finds, the report shows how a plant there would connect, what the fee would be, and how the substation’s category has moved across HEP ODS releases. A land check (€490 per project) tells you within five working days whether the substation behind an offered project still has room. Monitor (€199 per month) tells you when HEP ODS or HOPS opens or closes room at the substations you choose. See the products.
Sources
- Mrežna pravila distribucijskog sustava, NN 74/18, 52/20: čl. 28, čl. 47
- Zakon o tržištu električne energije, NN 111/21, 83/23, 17/25, 114/26
- Odluka o iznosu jedinične naknade za priključenje na mrežu (HERA), NN 45/26
- Metodologija za utvrđivanje naknade za priključenje na elektroenergetsku mrežu, NN 84/22
- Zakon o prostornom uređenju, NN 155/25: čl. 157 st. 3
- HEP ODS: Pravila o priključenju na distribucijsku mrežu (2023); information on connection possibilities for producers (release of November 2026)
- HOPS: information on connection possibilities to the transmission grid (March 2024)